Steel building kit or turnkey: assemble yourself, kit with assembly, or one contractor?
Updated on 24 October 2026
Three options, three scopes
The word kit means a calculated steel structure, fabricated in a workshop and delivered in bolt-together parts. What changes between options is who does the rest.
| Option | What you buy | What stays with you |
|---|---|---|
| Kit to assemble yourself | A steel structure with cladding and doors as quoted, delivered to site with drawings | Foundations and slab, permit and architect, crane or lifting equipment, assembly, finishing, electricity |
| Kit with assembly | The kit and its assembly by a professional crew (at Hallfort, partner crews, optional) | Foundations and slab, permit and architect, earthworks, electricity. The quote should say who provides the crane. |
| Turnkey | One contractor for design, permit file, foundation, building and assembly, for one price | Little, to be checked line by line (permit fees, soil survey, utility connections) |
Contractors publish offers of this type: one announces turnkey from idea to handover [17], another from permit to delivery [22]. A Turkish maker announces four levels, from engineering only to full assembly by a certified crew, with kit only and kit with supervision in between [21].
Hallfort will sell the kit, with optional assembly by partner crews still to be selected. Foundations, slab, permit, architect, earthworks and electricity are not included unless the quote says so. Hallfort coordinates with your architect. For a single contract that covers everything, turn to a general contractor.
Who does what
| Task | Kit to assemble yourself | Kit with assembly | Turnkey |
|---|---|---|---|
| Stability study and calculation note | Fabricator, coordinated by Hallfort | Fabricator, coordinated by Hallfort | The contractor |
| Steel fabrication and documents | Partner fabricator certified to EN 1090-1, EXC2 by default | Same | The contractor's fabricator: ask for its EN 1090 documents |
| Architect | You | You | An independent architect, appointed by you or by the contractor |
| Permit file | You and your architect. Hallfort supplies plans and calculation notes and coordinates | Same | The contractor, with the architect |
| Foundations and slab | You, with your contractor | You, with your contractor | The contractor |
| Delivery | Priced in the quote | Priced in the quote | Included in the price |
| Crane and lifting | You, unless the quote says otherwise | To be checked in the quote | The contractor |
| Assembly | You or your contractor | Partner crew | The contractor |
| Electricity and finishing | You | You | To be checked in the offer |
In Belgium, a hall that needs a permit in principle needs an architect. The 1939 law requires an architect for works that need a building permit (article 4) and makes the profession incompatible with that of contractor (article 6) [10]. The company that sells and assembles the kit therefore cannot be the project's architect. The exemptions consulted cover small annexes: in Flanders a garage or carport of at most 40 m², or a prefabricated structure of at most 50 m², with height conditions [11], and in Wallonia a carport of at most 40 m² under conditions [12]. See permits by region.
Whatever the option, ask who fabricates the steel and require the fabricator's EN 1090 certificate and declaration of performance. Among Belgian contractors, Clarinval announces EN 1090 certification for execution classes 1 to 3 [26] and Meynen up to EXC3 [27]. The kit sellers' pages we read do not mention it [2][3][4]. That is not proof that it is missing, only an observation about those pages. See EN 1090 and CE marking.
Skills, tools and time for self-assembly
A kit is assembled without welding. One Dutch seller describes assembling a light frame with pop-rivet pliers and a drill [2]. Another announces a team of 2 to 3 people, no welding, and offers assembly training [4]. Dutch sellers supply drawings, calculations and phone support [2][3].
Lifting is the real issue for a large hall. For a German hall, a 30 to 50 t mobile crane rents for 8,000 to 18,000 EUR for 7 to 14 days [7]. On a small building a lighter machine may do: ask the seller for the weight of the heaviest parts.
| Stage | Announced duration | Source |
|---|---|---|
| Lead time before a kit is delivered | 6 to 8 weeks at one Dutch seller, about 8 weeks at another, 10 to 15 weeks after signed plans at a Luxembourg seller | [3][4][1] |
| Turnkey hall | 14 weeks announced by one builder, 6 to 12 weeks for a simple hall at another (fabrication and erection) | [17][16] |
| Assembly of a small building | 1 to 2 days for a prefab garage, 2 days announced by a shed seller, under a week for a stock model | [15][20][19] |
| Crane on a large hall | 7 to 14 days of hire in Germany | [7] |
These are sellers' announcements, not measurements. The permit time comes on top and depends on the municipality.
Price differences, with published figures
| Option | Published figure, EUR/m² | Scope |
|---|---|---|
| Light kit to assemble yourself, large buildings | 61 to 133 | Closed hall of 1,110 m² at 61, of 227 m² at 101, insulated of 398 m² at 133 (calc). Delivery by quote, assembly by the client or partner firms [1]. |
| Dutch uninsulated kit to assemble yourself | 127 to 225 | 80 to 150 m² from 146 to 204, delivery in the Netherlands included (calc) [2]. 12 x 18 m at 205 to 225 [3]. 375 m² at 127, transport excluded (calc) [5]. Foundation and assembly excluded. |
| Dutch insulated kit to assemble yourself | 150 to 350 | 80 to 150 m² from 199 to 278 (calc) [2]. 300 m² from 220 to 350 depending on insulation [18]. 375 m² at 150 (calc) [5]. |
| Kit to assemble yourself, German maker | 250 to 310 | 500 m² uninsulated hall, assembly by the client [7]. |
| Insulated kit, delivered and erected, without foundation or permit | 380 to 520 | 500 m², German maker [7]. Eighteen offers from five makers: weighted quartile of 403 to 480, total spread of 362 to 624 [8]. Without foundation or permit. |
| Equipped insulated hall, Dutch contractor | 300 to 400 and more | 1,000 m² with insulation, slab and electrics [6]. |
| Complete project (turnkey), German maker | 810 | 364,500 EUR for 450 m² (calc), including hall 149,000, slab and earthworks 113,000, studies 49,500 and assembly 40,000 [9]. |
Assembly alone is priced at 89 EUR/m² for 450 m² in Germany (40,000 EUR excl. VAT, steel and cladding) [9], at 50 to 70 EUR/m² in a French consumer guide [13] and at 10 to 15% of the steelwork cost in the UK [14]. Adding 50 to 89 EUR/m² to a Dutch uninsulated kit of 146 to 225 gives an order of magnitude of about 196 to 314 EUR/m² assembled, crane extra (calc, to be verified).
A turnkey price is not comparable with a kit price: it buys more. Compare the scopes, not the prices per m². See the price per m² by type.
The risks of each option
- Kit to assemble yourself. The kit price contains no assembly, crane or foundation. One maker advises allowing 15 to 25% on top of the hall price for contingencies and options [7]. Labour and crane do not appear on the quote, but they exist.
- Kit with assembly. Check who provides the crane, who prepares access and who answers for a defect in the foundation. These points belong in the quote.
- Turnkey. The Belgian contractors we consulted publish no prices [26][27]. A global price is hard to compare line by line: ask for the breakdown.
- All options. Permit, architect and foundation remain necessary. A Dutch seller presents its models as permit-free subject to local rules [2]: check with your municipality before buying.
- Steel price. HRC rose about 24% in a year [23][24] and zinc 31% [25]. An indicative price can move before the binding price in the quote.
How to choose
- A kit to assemble yourself suits a simple building, without heavy insulation, with a contractor or crew able to lift and bolt, and with time.
- A kit with assembly suits you if you want to fix the price of structure and assembly without managing the crew. Foundations and permit stay your files.
- Turnkey suits a large insulated hall, a tight schedule or a client who wants a single contact for everything, foundation included.
For a first figure, use the configurator: it gives an indicative range excl. VAT. The binding price is in a quote, after a stability study for your site. See also foundations and the price index.
Frequently asked questions
Can I assemble a steel building kit myself?
Yes for a simple building. Assembly is done without welding, with a team of 2 to 3 people at one seller [4] or pop-rivet pliers and a drill for a light frame [2]. A large hall needs a crane, 8,000 to 18,000 EUR for 7 to 14 days in Germany [7].
How long does it take to assemble a steel building kit?
Sellers announce 1 to 2 days for a prefab garage [15] and 2 days for a shed [20]. On a large hall the crane is hired for 7 to 14 days [7]. These are announcements, to be confirmed for your building.
Do I need a permit for a kit building?
As a rule yes. The exemptions consulted cover small annexes, for example a carport of at most 40 m² in Wallonia under conditions [12]. One seller presents its models as permit-free subject to local rules [2]. See the guide on permits by region.
What does a turnkey offer include?
It depends on the contractor. Some announce permit to delivery [22] or idea to handover [17]. Ask for the detail: foundation, slab, permit fees, soil survey and utility connections.
How much cheaper is a kit than turnkey?
A kit you assemble yourself is published at about 60 to 150 EUR/m² excl. VAT for large buildings and 127 to 225 for complete Dutch kits [1][2][3], against 380 to 520 for a 500 m² insulated hall delivered and erected without foundation or permit [7], and about 810 for a complete project [9]. The scopes differ: the gap covers assembly, crane, engineering, margin and insulation.
Sources
- Luxembourg kit seller, steel buildings in kit form (website), accessed on 2026-10-24
- Huisman, permit-free shed kits (price per model), accessed on 2026-10-24
- Optistaal, what does a shed cost (2026 table), accessed on 2026-10-24
- Frisokit, steel buildings to assemble yourself, accessed on 2026-10-24
- Finish Building, cost of a custom shed, accessed on 2026-10-24
- Visser Dokkum, cost of a 1,000 m² shed, accessed on 2026-10-24
- SmartHalls, steel hall prices 2026 (26 Jan 2026), accessed on 2026-10-24
- Rechner-Portal, hall cost calculator (8 Oct 2026), accessed on 2026-10-24
- HALTEC, what a hall costs (09/2025), accessed on 2026-10-24
- Law of 20 February 1939 on the protection of the title and profession of architect (Justel), accessed on 2026-10-24
- Vlaanderen, exemption from the architect requirement, accessed on 2026-10-24
- Walloon Region, list of acts exempt from a permit (CoDT), accessed on 2026-10-24
- La Maison Saint-Gobain, steel frame guide (15 Jul 2025), accessed on 2026-10-24
- SCI SteelConstruction.info, cost of structural steelwork, accessed on 2026-10-24
- D-Lux Systemen, prefab garage, accessed on 2026-10-24
- Novicon, cost of a steel structure, accessed on 2026-10-24
- Astron Buildings, fixed-price steel halls, accessed on 2026-10-24
- Optistaal, building an industrial hall, accessed on 2026-10-24
- Zelfbouwloodsen.nl, shed kits in stock, accessed on 2026-10-24
- Snelbouwloods, sheds to assemble yourself, accessed on 2026-10-24
- SerBuild, steel kits for the Netherlands, accessed on 2026-10-24
- Staalbouw DtB, agricultural steel construction, accessed on 2026-10-24
- Eurometal, northern European HRC prices (19 Oct 2026), accessed on 2026-10-24
- Eurometal, northern European HRC prices (27 Oct 2025), accessed on 2026-10-24
- Dr. Web, zinc price (July 2026), accessed on 2026-10-24
- Clarinval Constructions, turnkey agricultural halls, accessed on 2026-10-24
- Metaalconstructie Meynen, steel constructions, accessed on 2026-10-24